Approve attendance corrections
Answer an employee who forgot a punch or punched at the wrong time, and fix the day.
- Product version
- Web v2.4.1
- Last updated
- 2026-11-22
Who can do it
HR Admin or Company Owner, and managers for their direct reports.
Before you start
- The employee sent a correction request from My Attendance. Check in for the day
Steps
- 1
Open Attendance > Correction requests. Each request shows the employee, the Date and their Note.
- 2
Click Answer on the request.
Screenshot could not be loaded- 1
- 3
Under Decision, choose Approve and enter the Check-in time and Check-out time to record; leave both empty to approve without changing attendance.
- 4
Or choose Reject. Write a Reply to the employee in either case, and save.
Screenshot could not be loaded- 3
Expected result
The request shows Approved or Rejected, and the employee is told. Approved times are recorded as manual punches on that day, on the company’s clock.
If something goes wrong
| Message or symptom | What to do |
|---|---|
| Cannot record attendance for <month>: payroll for this period has been finalized. | That month is closed. Make the adjustment in the next payroll. |
What comes next
How it flows
Self check-in with geofence
flowchart TD
A[Employee taps Check in] --> A2{Same punch in the last 60 s?}
A2 -- yes --> OK0[Returns the same punch]
A2 -- no --> A3{Approved full-day leave?}
A3 -- yes --> X2[Refused: on leave]
A3 -- no --> B{Month payroll finalized?}
B -- yes --> X[Refused: period locked]
B -- no --> C{Geofence policy}
C -- off --> OK[Punch saved]
C -- flag / block --> D{Location shared?}
D -- no --> Y[Refused: location required]
D -- yes --> E{Inside a work location radius?}
E -- yes --> OK
E -- no, flag --> F[Saved, marked outside fence for HR]
E -- no, block --> Z[Refused: N m away from site]Self check-in with geofence: steps in text
- Employee taps Check in
- Same punch in the last 60 s?
- Same punch in the last 60 s?
- yes Returns the same punch
- no Approved full-day leave?
- Returns the same punch
- Approved full-day leave?
- yes Refused: on leave
- no Month payroll finalized?
- Refused: on leave
- Month payroll finalized?
- yes Refused: period locked
- no Geofence policy
- Refused: period locked
- Geofence policy
- off Punch saved
- flag / block Location shared?
- Punch saved
- Location shared?
- no Refused: location required
- yes Inside a work location radius?
- Refused: location required
- Inside a work location radius?
- yes Punch saved
- no, flag Saved, marked outside fence for HR
- no, block Refused: N m away from site
- Saved, marked outside fence for HR
- Refused: N m away from site
- Lateness is judged against the assigned shift and its grace period, on the company’s own timezone.
- On a night shift, the morning punch closes the shift that started the evening before.
- Tapping Check in twice within a minute does not create a second punch, and you cannot check in on a day of approved leave.
Attendance correction request
flowchart LR
A[Employee: Request correction with a note and proposed times] --> B[Pending · HR and line manager notified]
B --> C{HR answers}
C -- Approve --> D[Proposed times applied as manual punches]
C -- Reject + reply --> E[Rejected with the reply]
D --> F[Employee notified]
E --> FAttendance correction request: steps in text
- Employee: Request correction with a note and proposed times
- Pending · HR and line manager notified
- Pending · HR and line manager notified
- HR answers
- HR answers
- Approve Proposed times applied as manual punches
- Reject + reply Rejected with the reply
- Proposed times applied as manual punches
- Employee notified
- Rejected with the reply
- Employee notified
- Employee notified
- HR approves the request, optionally with the corrected times, or rejects it with a reply.